Red Tape Is Slowing Canada’s Fast Chargers, Industry Survey Says

Tesla Supercharger stall with red and white Tesla branding next to a white Model S charging in a Markham, Ontario parking lot

If it feels like new fast chargers take forever to open in Ontario, the companies building them say you’re right, and they have numbers to back it up. A new survey from the Canadian Charging Infrastructure Council (CCIC), the national industry association for EV charging, says municipal rules and utility hookups are slowing public fast-charger projects across the country, and in some cases killing them outright.

What the survey found

The CCIC released the report, Hearing from the Experts: Survey Findings on Municipal Approvals, Utility Connections, and Public Fast-Charging Deployment in Canada, on November 4. It is based on responses from nine organizations: seven charging network operators and two engineering and construction contractors, with projects in eight provinces, led by Ontario, Quebec and British Columbia. Together they reported commissioning 217 public fast-charging sites over the previous 24 months.

The key findings, all self-reported by the respondents:

  • Parking minimums are the top delay. 78% said municipal parking requirements had held up projects. Chargers take up parking stalls, which can leave a property below the number of spaces a bylaw demands.
  • Every city does it differently. 88% reported moderate to extreme variation in how municipalities in the same province handle the same kind of approval.
  • Sites are being abandoned. Seven respondents walked away from a combined 54 sites over two years, even after signing agreements with property owners. Ten were mainly due to municipal delays or denials, and 17 to utility connection delays or costs.
  • Delays cost money. 71% estimated cost increases of 10% to 25% on projects that were significantly delayed but still went ahead.
  • Three months should be enough. 89% said a permit for adding chargers to an existing parking lot should take under three months. Electric Autonomy Canada, which reviewed the report, noted that none of the respondents who reported typical timelines got approvals that fast, with waits of three to 18 months.

The CCIC is asking municipalities to count charging stalls toward parking requirements, create a fast “minor works” approval path for simple retrofits, publish clear requirements with a single point of contact, and commit to deciding complete applications within three months.

Ontario has its own red tape problem

The survey echoes a September report from The Atmospheric Fund (TAF), a Toronto-based climate agency that is leading Toronto’s Public EV Charging Plan. TAF’s Red Tape Reduction Opportunities for the Province of Ontario says some charging project approvals in the province have taken more than 30 months, and that utility preliminary design approvals have taken up to 18 months for some gas station owners.

TAF points to a Hamilton example: On The Run Charging planned five DC fast-charging projects in the city, but repeated municipal and utility delays stalled them, and the report says they are now unlikely to proceed. TAF wants Ontario’s Ministry of Transportation to give municipalities a toolkit that defines how chargers are classified in zoning bylaws, or to adopt a province-wide EV readiness policy similar to Quebec’s recent building code changes. It also suggests opening surplus public land and parking to charging operators and waiving parking fees for drivers using those chargers, which it estimates could cut urban charging costs by 33% to 65%.

There are some early fixes. Electric Autonomy reports that Toronto Hydro is running a pilot, capped at 10 projects through the end of 2027, that supplies 480-volt service directly to public fast-charging sites. Most fast chargers run on 480 volts, while the utility’s service has typically been 600 volts, forcing operators to buy their own step-down transformers.

Tesla owners have seen this firsthand

Neither report names Tesla, and the CCIC doesn’t say which companies took part. But the pattern will look familiar to anyone who follows Supercharger openings. In Gatineau, eight V4 posts were installed by November 2025, then the site sat idle for nearly a year before Tesla could energize it; we covered the Gatineau opening on November 8. Drive Tesla Canada reports that Ontario Supercharger projects in Toronto, Port Hope, Hamilton, Madoc and Orangeville are still under construction, and EVcharts lists London and Britt, on Highway 69, among sites in planning.

Money isn’t the only bottleneck, either. Ottawa’s Budget 2026 put new funding behind tens of thousands of additional public chargers (see our Budget 2026 breakdown), but the industry’s message is that funded chargers still have to get through local permits and utility queues before anyone can plug in.

What it means for Canadian owners

  • Plan winter trips around what’s open today. A site that shows up on Tesla’s map as “coming soon” can take many months, or longer, to open. Use the in-car trip planner and the Find Us map, not construction photos.
  • Home charging is still your best friend. TAF notes more than 31% of Ontarians live in condos and apartments, where charging access is harder. If you can charge at home or work, that’s the most reliable option all winter.
  • Speak up locally. Most of the fixes in both reports, like parking rules and permit timelines, sit with your city or town. If a charger project near you is stuck, that’s a fair question for your councillor.
  • Vote for sites. Tesla’s Supercharger voting shows where owners want stations, even if local approvals still set the pace.

Which Ontario charging gap would you fix first? Tell 18.5K owners in Tesla Model Y & 3 [Ontario, Canada], where members share charging tips and road-trip routes every day. Come join us!

On X? Join our community Tesla Model* [Ontario, Canada] too.

Sources

About the author

Sivachandran Bharathi — Tesla Canada Group Admin · Lead Software Engineer, MASc Computer Engineering Connect on LinkedIn